8.5
Wildlife
Canyon Ridge is in a location where the
town meets the forest and care should be taken during and after
construction to preserve wildlife habitat and avoid disturbance
to wildlife. Pets must be kept under control and not allowed
to chase wildlife. Food and garbage should never be left outside
and barbecues should be kept clean. It is unlawful to feed
wildlife.
8.6 Other buildings & site structures
Site structures such as gazebos, patios,
decks, retaining walls, and planters should be designed, be
appropriate to the scale and aesthetics of the house, and compliment
the existing and proposed landscapes. Storage sheds and other
auxiliary buildings must be placed at the side or to the rear
of the property. Their appearance must be in accordance with
the guidelines described herein and the maximum size permitted
is 10’X12’. Carports are not permitted and garages
must be attached to the residence with a breezeway as a minimum,
with the exception of carriage lots with possible development
above the garage.
9. Construction Timing
The Owner covenants to obtain design approval
from the Developer and commence construction of their property
within 2 years from the date title is conveyed from the Developer
to the Owner. It is recommended that Owners start their design
process at least 6 months before they plan to start construction.
Should the owner fail to start construction within the time
allowed the Developer reserves the right to purchase the lot
from the buyer free from any encumbrances for 90% of the original
sale price.
Construction must be completed and a final
inspection obtained from the Town of Golden within 18 months
of construction start. Landscaping must be completed within
24 months from the start of construction. Should the owner
fail to complete construction within the time allowed an amount
equal to 2% of the original lot sale price, will be payable
to the Developer. A further 1% will be paid to the Developer
at the beginning of each following month if construction has
not been completed and final inspection has not been obtained.
10. Construction Regulations
10.1 Noise & Working Hours
Construction work may only be carried out
between the hours of 7:00 am and 9:00 pm Monday to Saturday
and 12:00 Noon to 9:00 pm on Sundays and holidays. Builders
and lot owners must use reasonable efforts to minimise noise
and dust during construction.
10.2 Contractor Parking & Deliveries
Where possible all construction vehicles
should be parked within the lot boundary. Overnight street
parking is not permitted except by permit from the developer.
10.3 Damage
Lot owners will be held responsible and
will pay for any damage to common (Community Association) property
and other lots. Owners and their contractors should take particular
care to avoid damage to the road surface and underground services
when parking and unloading heavy equipment such as gravel trucks
and excavators. Prior to start of construction each lot owner
shall complete an inspection report to insure any damage to
the common property adjacent to the lot is documented. The
developer will inspect any noted damage and sign off liability.
Final inspection of the common property will be completed with
the lot inspection, and if any damage exists, the cost of repair
will be deducted from the lot damage deposit. The lot owner
is liable for any costs of repair over the damage deposit amount.
10.4 Construction Debris and Garbage
Construction debris or garbage may not
be burned, buried or dumped anywhere on the Canyon Ridge site.
Owner and contractors must clean up garbage and debris on the
lot at the end of each day and generally ensure the site is
clean and tidy. So as not to attract wildlife, no food or food
waste may be left unattended on site under any circumstances.
Constructions garbage bins are required during construction.
Concrete mixer clean out must be contained on site.
|